Concurrent Amendments to Eight Electricity Market Regulations

22.10.2026 Fuat Sarı
% 0

Amendments made by the Energy Market Regulatory Authority (EMRA) to eight regulations concerning balancing and settlement, licensing, electricity storage activities, renewable energy support mechanisms and system use in the electricity market entered into force through publication in the Official Gazette dated 19.10.2026 and numbered 33405 and in the Official Gazette dated 21.10.2026 and numbered 33407.

Amendments to the Electricity Market Balancing and Settlement Regulation

  • It was stipulated that load increase and load reduction bids in the balancing power market will be submitted on a settlement period basis rather than an hourly basis.
  • Thermal power plants are required to notify the System Operator of their bid quantities based on their ramp-up and ramp-down curves. These curves may be updated up to four times per calendar year. The issuance of instructions to operating thermal balancing units based on these curves will commence on 01.01.2027.
  • Priority rules for implementing emergency instructions concerning unlicensed electricity generation plants with an operational installed electrical capacity of 900 kW or more were established, together with coordination obligations for the relevant entities. Aggregators are also required to establish remote control mechanisms for unlicensed generation plants connected to the distribution system within their portfolios.
  • Generation plants may only be registered in an aggregator's portfolio if at least one generation unit has received acceptance from the Ministry and the settlement-related registrations for the relevant injection and withdrawal units have been completed by the transfer date.
  • With the amendment dated 21.10.2026, the restrictions on market activities applicable to market participants that fail to provide sufficient collateral or replenish their collateral without settling their outstanding default payments were extended to cover bilateral agreements and the electricity futures market.

The Regulation is available here.

Amendments to the Electricity Market Connection and System Use Regulation

  • Consumers seeking to install electricity storage facilities with an installed capacity exceeding their contracted power are now required to install an automatic power control unit and an electricity disconnection system to prevent electricity from being supplied to the grid and the contracted power limit from being exceeded.
  • Generation license holders may not request disconnection from the distribution system unless their licenses have expired or been revoked. However, where a generation plant connected to the distribution system seeks connection to the transmission system, a disconnection request may be submitted once the connection point specified in the relevant license holder's license has been amended.
  • Collateral required for the use of the distribution system may now be provided in the form of electronic letters of guarantee in addition to cash or definitive bank letters of guarantee with no expiry date. Where an increase in collateral is required, the additional collateral must be provided within 10 business days following written notification. Excess collateral must be returned within 10 business days upon request.

The Regulation is available here.

Amendments to the Regulation Concerning Unlicensed Electricity Generation in the Electricity Market

  • Distribution companies as well as organized industrial zones and industrial zones holding distribution licenses have been authorized to remotely control certain unlicensed electricity generation plants to implement emergency instructions. Plant owners must be notified within 15 minutes after the emergency has ended and will be responsible for re-energizing their plants.
  • Storage units integrated into unlicensed generation plants may be installed up to the electrical power of the generation plant, without any storage energy capacity limitation.
  • Where unlicensed generation plants fail to comply with emergency load reduction instructions issued by the System Operator, no payment will be made for the generation corresponding to the unfulfilled portion of the instruction. In addition, amounts calculated based on the applicable tariffs will be collected from the relevant unlicensed generators.
  • The relevant unlicensed generators have been granted a 60-day period to apply for amendments to their connection agreements. If no application is submitted within this period, the relevant procedures will be carried out in accordance with the existing connection agreements.

The Regulation is available here.

Amendments to the Regulation on the Certification and Support of Renewable Energy Resources

  • It was stipulated that electricity generated and stored at a generation plant may benefit from support under the Renewable Energy Resources Support Mechanism (YEKDEM), provided that virtual records confirm that the electricity was generated and stored after the plant's participation in YEKDEM. However, electricity stored before participation in YEKDEM will not be eligible for support payments, subject to the exceptions under the relevant legislation.
  • The amount of electricity drawn from the grid and stored that is deemed to be supplied back to the grid without benefiting from YEKDEM support will be determined based on virtual records. In addition, the total amount of electricity recorded in the virtual records may not exceed the storage capacity and the records must be updated proportionally if additional electricity is stored after the capacity has been reached.
  • The formulas used to calculate YEKDEM support payments were updated. The calculations will also take into account the costs associated with unlicensed generation arising from non-compliance with emergency instructions. In addition, generation plants commissioned after 30 June 2021 that are not registered under YEKDEM may benefit from domestic component support subject to certain conditions.

The Regulation is available here.

Amendments to the Electricity Market Licensing Regulation

  • It was stipulated that the collateral submitted in connection with license applications for electricity generation plants with storage facilities will not be returned until the entire generation plant becomes operational. For the return of collateral relating to storage units, the capacity of the commissioned unit, in terms of power, will be taken into account.
  • Supply license holders other than incumbent supply companies, and aggregation license holders, are prohibited from using trade names, brands or logos that may create the impression that they are affiliated with distribution companies.
  • Where an event previously recognized by the Board as force majeure becomes permanent and prevents the completion of the investment, requests for the postponement, suspension or removal of obligations will no longer be assessed under the same provision.

The Regulation is available here.

Amendments to the Regulation on Electricity Storage Activities in the Electricity Market

  • Consumers may now install electricity storage facilities with an installed capacity exceeding their contracted power if a favorable connection opinion is obtained from the relevant network operator and the storage facility is located at the same metering point as the consumption facility.
  • Such facilities must be equipped with an automatic power control unit and an electricity disconnection system to prevent electricity from being supplied to the grid and to ensure that the contracted power limit is not exceeded when electricity is withdrawn from the grid.

The Regulation is available here.

Amendments to the Electricity Market Ancillary Services Regulation

  • The rules governing the calculation of payments to aggregators providing demand-side participation services were revised. Capacity payments will be calculated by taking into account the proportion of hours during which aggregators were determined not to have participated in activation instructions to the total number of instructed hours during the critical month.
  • Where the actual load reduction exceeds the instructed amount by up to 50%, the service will be deemed to have been provided. If this threshold is exceeded, the service will only be deemed to have been provided if approval is obtained from the Transmission System Operator at least one hour before the activation instruction begins.
  • The capacity payments of aggregators that fail to participate in activation instructions will be reduced in proportion to the hours of non-participation during the critical month relative to the total number of instructed hours.
  • The implementation of ancillary service performance tests and the issuance of test certificates or reports by the Turkish Electricity Transmission Corporation (TEİAŞ) has been postponed until 31 December 2026.

The Regulation is available here.

Amendments to the Regulation on Electricity Market Activities of Organized Industrial Zones and Industrial Zones

  • Legal entities responsible for organized industrial zones and industrial zones holding distribution licenses are now required to comply with load reduction instructions concerning unlicensed generation plants communicated by the incumbent supply companies, as well as emergency instructions issued by TEİAŞ.
  • These legal entities are required to share information on unlicensed generation plants connected to distribution systems and the implementation of instructions with the incumbent supply companies. They must also submit the data requested by TEİAŞ under emergency measures in a timely and complete manner. Failure to comply with these obligations will be subject to the sanctions set out in Article 16 of Electricity Market Law No. 6446.

The Regulation is available here.

Make us your preferred source on Google
See Erdem & Erdem publications featured in your Google Search results.
Add as preferred source More from erdem-erdem.av.tr

All rights of this article are reserved. This article may not be used, reproduced, copied, published, distributed, or otherwise disseminated without quotation or Erdem & Erdem Law Firm's written consent. Any content created without citing the resource or Erdem & Erdem Law Firm’s written consent is regularly tracked, and legal action will be taken in case of violation.

Other Contents

EMRA Issued a Provisional Measure for Unlicensed Generation Facilities That Have Completed Their Ten-Year Support Period
Legal Developments
EMRA Issued a Provisional Measure for Unlicensed Generation Facilities That Have Completed Their Ten-Year Support Period

The Energy Market Regulatory Board’s Decision No. 14671 dated 18 June 2026 (Board Decision) was published in the Official Gazette dated 20 June 2026 and numbered 33286…

Energy Law 22.06.2026
Procedures and Principles Established for Unlicensed Electricity Generation Facilities That Have Completed Their Ten-Year Support Period
Legal Developments
Procedures and Principles Established for Unlicensed Electricity Generation Facilities That Have Completed Their Ten-Year Support Period

Resolution of the President No. 11415 (Resolution) entered into force upon its publication in the Official Gazette dated 13 June 2026 and numbered 33279. The Resolution sets forth the price applicable to surplus electrical energy generated by electricity generation…

Energy Law 16.06.2026
The Procedures and Principles Regarding Net-Metering for Unlicensed Electricity Generation and Consumption Facilities Published
Legal Developments
The Procedures and Principles Regarding Net-Metering for Unlicensed Electricity Generation and Consumption Facilities Published

The “Procedures and Principles Regarding the Net-Metering Transactions of Unlicensed Electricity Generation Facilities and Their Associated Consumption Facilities” (Procedures and Principles), enacted by the decision of the Energy Market Regulatory Board…

Energy Law 05.05.2026
Significant Amendments Introduced to the Charging Service Regulation
Legal Developments
Significant Amendments Introduced to the Charging Service Regulation

With the Regulation Amending the Charging Service Regulation (Regulation) published in the Official Gazette dated March 23, 2026, and numbered 33202, certain amendments have been introduced to the regulatory framework governing charging services for electric…

Energy Law 24.03.2026
Regulation on Transparency and Market Abuse in Energy and Environmental Markets Published
Legal Developments
Regulation on Transparency and Market Abuse in Energy and Environmental Markets Published

The Regulation on Transparency and Market Abuse in Energy and Environmental Markets (Regulation), prepared by the Energy Market Regulatory Authority (Authority), was published in the Official Gazette dated 14.02.2026 and numbered 33168…

Energy Law 19.02.2026
Concurrent Updates to Seven Regulations in the Energy Sector
Legal Developments
Concurrent Updates to Seven Regulations in the Energy Sector

Through the regulations published in the Official Gazette dated December 29, 2025, and numbered 33122, comprehensive amendments have been introduced to the following regulations relating to the energy sector, primarily the electricity market and including renewable energy…

Energy Law 31.12.2025
Regulation on the Procedures and Principles Regarding the Use and Leasing of Water Surfaces for the Establishment of Floating Solar Power Plants Published
Legal Developments
Regulation on the Procedures and Principles Regarding the Use and Leasing of Water Surfaces for the Establishment of Floating Solar Power Plants Published

The Regulation on the Procedures and Principles Regarding the Use and Leasing of Water Surface in the Establishment of Floating Solar Power Plants (Regulation) entered into force after being published in the Official Gazette dated 10.12.2025 and numbered 33103. The Regulation includes comprehensive…

Energy Law 12.12.2025
Amendments to the Regulation on Unlicensed Electricity Generation in the Electricity Market
Legal Developments
Amendments to the Regulation on Unlicensed Electricity Generation in the Electricity Market

The Regulation Amending the Regulation on Unlicensed Electricity Generation in the Electricity Market Amendment Regulation came into effect through publication in the Official Gazette dated 25.11.2025 and numbered 33088...

Energy Law 27.11.2025
Amendment to the Electricity Market Licensing Regulation
Legal Developments
Amendment to the Electricity Market Licensing Regulation

With the Regulation on Amendments to the Electricity Market Licensing Regulation, published in the Official Gazette No. 32966 dated July 25, 2025, and entered into force on the same date, amendments have been made regarding the changes in the shareholding structure of legal entities holding a pre-license...

Energy Law 01.08.2025
Amendments to Various Regulations on the Electricity Market
Legal Developments
Amendments to Various Regulations on the Electricity Market

In the Official Gazette dated 21.01.2025 and numbered 32789 (Official Gazette), regulations that envisage many amendments to various regulations in the electricity market were published and entered into force...

Energy Law 24.01.2025
Regulation on Aggregation Activities in the Electricity Market
Legal Developments
Regulation on Aggregation Activities in the Electricity Market

The aggregation activity was included, at a high level, in the Electricity Market Law numbered 6446 (EML) on 22.12.2022 and was articulated as an electricity market activity. The fourth paragraph of Article 12/A of the EML, stated that the procedures and principles regarding the aggregation activity were to be...

Energy Law 17.12.2024
Amendments to the Regulation on Unlicensed Electricity Generation in the Electricity Market
Legal Developments
Amendments to the Regulation on Unlicensed Electricity Generation in the Electricity Market

The Regulation Amending the Regulation on Unlicensed Electricity Generation in the Electricity Market (Regulation Amendment) entered into force through publication in the Official Gazette dated 14.05.2024 and numbered 32546. The important issues in the Regulation Amendment are summarized below...

Energy Law 16.05.2024
Regulation on Electricity Market Measurement Systems
Legal Developments
Regulation on Electricity Market Measurement Systems

The Regulation on Electricity Market Measurement Systems (Regulation) was published in the Official Gazette dated 28.12.2023 and numbered 32413.The Regulation articulates the issues regarding the determination, installation, and operation of all measurement systems, including meters within the scope...

Energy Law 28.12.2023
Regulation on Measures Regarding Natural Gas Market Distribution Licenses has been Published
Legal Developments
Regulation on Measures Regarding Natural Gas Market Distribution Licenses has been Published

The Regulation on Measures Regarding Natural Gas Market Distribution Licenses (Regulation) entered into force after being published in the Official Gazette dated 19.08.2023 and numbered 32284. The Regulation covers the procedures and principles regarding the measures to be taken for the protection of natural...

Energy Law 21.08.2023
Amendments Regarding Charging Services
Legal Developments
Amendments Regarding Charging Services

The Regulation Amending the Charging Service Regulation entered into force through publication in the Official Gazette dated 28.07.2023 and numbered 32262 and the Regulation Amending the Regulation on Workplace Opening and Operating Licenses (Amending Regulations) entered into force through publication...

Energy Law 31.07.2023
The Energy Market Regulatory Authority Decision on the Electricity Generation in Free Zones
Legal Developments
The Energy Market Regulatory Authority Decision on the Electricity Generation in Free Zones

The Energy Market Regulatory Authority’s (EMRA) Decision (Decision) dated 20.07.2023 and numbered 11960 was published in the Official Gazette dated 25.07.2023 and numbered 32259. With the Decision, some issues regarding electricity generation in free zones have been clarified...

Energy Law 25.07.2023
The Procedures and Principles Regarding Offsetting for Generation and Consumption Facilities Located in Different Distribution Regions or Assigned Supplier Company Regions
Legal Developments
The Procedures and Principles Regarding Offsetting for Generation and Consumption Facilities Located in Different Distribution Regions or Assigned Supplier Company Regions

The Procedures and Principles Regarding Offsetting for Generation and Consumption Facilities Located in Different Distribution Regions or Assigned Supplier Company Regions (Procedures and Principles), adopted by the Energy Market Regulatory Authority’s decision dated 22.06.2023 and numbered 11917, is...

Energy Law 26.06.2023
The Communiqué Amending the Communiqué on the Implementation of Energy Performance Contracts in Public Sector
Legal Developments
The Communiqué Amending the Communiqué on the Implementation of Energy Performance Contracts in Public Sector

The Communiqué Amending the Communiqué on the Implementation of Energy Performance Contracts in Public Sector (Communiqué) entered into force through publication in the Official Gazette dated 23.06.2023 and numbered 32230. The amendments made by the Communiqué are...

Energy Law 23.06.2023
"Photovoltaic Cells" Imported for Solar Panels are Included in the Scope of Import Surveillance
Legal Developments
"Photovoltaic Cells" Imported for Solar Panels are Included in the Scope of Import Surveillance

Through the promulgation of the Communiqué on the Implementation of Surveillance in Imports (Communiqué No: 2023/2) (Communiqué) published in the Official Gazette dated 27 January 2023 and No. 32086, the procedures and principles regarding the surveillance implementation of photovoltaic cells...

Energy Law 27.01.2023
Amendment on The Regulation on Technical Evaluation of Solar Energy Based Electricity Generation Applications
Legal Developments
Amendment on The Regulation on Technical Evaluation of Solar Energy Based Electricity Generation Applications

The Regulation Amending the Regulation on Technical Evaluation of Solar Energy Based Electricity Generation Applications (Regulation) published in the Official Gazette dated 17 January 2023 and numbered 32076 entered into force...

Energy Law 17.01.2023
Law Amending the Electricity Market Law, Certain Laws and Decree No. 375 is Published
Legal Developments
Law Amending the Electricity Market Law, Certain Laws and Decree No. 375 is Published

The Law Amending the Electricity Market Law, Certain Laws and Decree Law No. 375 (Omnibus Law) entered into force following its publication in the Official Gazette dated 28.12.2022 and numbered 32057. The Omnibus Law introduced significant amendments to the Law on Privatization Practices numbered...


Energy Law 29.12.2022
Mining Regulation has been Published
Legal Developments
Mining Regulation has been Published

Mining Regulation (Regulation) entered into force following its publication in the Official Gazette dated December 11, 2022 and numbered 32040. Through this regulation, the mining regulation published in the Official Gazette dated September 21, 2017 and numbered 30187 (Previous Regulation) has been abrogated... 

Energy Law 13.12.2022
The Expected Regulatory Changes as to Storage Activities in the Electricity Market Entered Into Force
Legal Developments
The Expected Regulatory Changes as to Storage Activities in the Electricity Market Entered Into Force

Several changes have been made on Electricity Generation Regulation in the Electricity Market, the Regulation on Connection and System Usage in the Electricity Market, Electricity Market Balancing and Settlement Regulation, Regulation on Storage Activities in the Electricity Market, Electricity Grid...

Energy Law 21.11.2022
The Regulation Amending the Regulation on Unlicensed Electricity Generation in the Electricity Market Entered into Force
Legal Developments
The Regulation Amending the Regulation on Unlicensed Electricity Generation in the Electricity Market Entered into Force

The Regulation on Amending the Regulation on Unlicensed Electricity Production in the Electricity Market entered into force following its publication in the Official Gazette with the number 31970 on October 1, 2022...

Energy Law 03.10.2022
The Regulation Amending the Regulation on Unlicensed Electricity Generation in the Electricity Market Has Been Published in the Official Gazette
Legal Developments
The Regulation Amending the Regulation on Unlicensed Electricity Generation in the Electricity Market Has Been Published in the Official Gazette

The Regulation (“Amending Regulation”) Amending the Regulation on Unlicensed Electricity Generation in Electricity Market ("Regulation") and Energy Market Regulatory Board’s decision dated 04.08.2022 numbered 11098 (“Decision”) have been published in the Official Gazette dated 11.08.2022 and...

Energy Law 12.08.2022
Charging Service Regulation Has Been Published
Legal Developments
Charging Service Regulation Has Been Published

With the Charging Service Regulation (“Regulation”) which has been published in the Official Gazette dated 2nd April 2022 and No. 31797, the procedures and principles regarding the establishment of charging units and stations where electrical...

Energy Law 04.04.2022
The Regulation on Environmentally Responsible Design of Energy-Related Products Entered into Force
Legal Developments
The Regulation on Environmentally Responsible Design of Energy-Related Products Entered into Force

Regulation on Environmentally Responsible Design of Energy-Related Products entered into force through its publication in the Official Gazette dated 05.02.2022 and numbered 31741. The Regulation...

Energy Law 07.02.2022
Presidential Decree on the Facilities Engaged in Production Activity Based on Renewable Energy Resources
Legal Developments
Presidential Decree on the Facilities Engaged in Production Activity Based on Renewable Energy Resources

Presidential Decree on the Facilities Engaged in Production Activity Based on Renewable Energy Resources

Energy Law 18.09.2020
Supplier of Last Resort Tariff is Amended
Legal Developments
Supplier of Last Resort Tariff is Amended

Supplier of Last Resort Tariff is Amended

Energy Law 1.10.2020
Energy Disputes Arbitration Center (EDAC) Established
Legal Developments
Energy Disputes Arbitration Center (EDAC) Established

Energy Disputes Arbitration Center (EDAC) Established

Energy Law 27.10.2020
Takasbank has been granted an Operating Certificate regarding Future Electricity Market and Organized Renewable Energy Source Guarantee Market
Legal Developments
Takasbank has been granted an Operating Certificate regarding Future Electricity Market and Organized Renewable Energy Source Guarantee Market

Takasbank has been granted an Operating Certificate regarding Future Electricity Market and Organized Renewable Energy Source Guarantee Market

Energy Law 25.11.2020
The law amendment concerning regulations in the natural gas, electricity, renewables and mining has entered into force
Legal Developments
The law amendment concerning regulations in the natural gas, electricity, renewables and mining has entered into force

The law amendment concerning regulations in the natural gas, electricity, renewables and mining has entered into force

Energy Law 2.12.2020
The Eligible Consumer Limit in Electricity was reduced
Legal Developments
The Eligible Consumer Limit in Electricity was reduced

The Eligible Consumer Limit in Electricity was reduced

Energy Law 22.12.2020
Amendments to the Renewable Energy Resources Support Mechanism
Legal Developments
Amendments to the Renewable Energy Resources Support Mechanism

Amendments to the Renewable Energy Resources Support Mechanism

Energy Law 2.02.2021
Significant Amendments on the Electricity Market Balancing and Settlement Regulation and Electricity Market Consumer Services Regulation
Legal Developments
Significant Amendments on the Electricity Market Balancing and Settlement Regulation and Electricity Market Consumer Services Regulation

Significant Amendments on the Electricity Market Balancing and Settlement Regulation and Electricity Market Consumer Services Regulation

Energy Law 22.02.2021

For creative legal solutions, please contact us.